Ring-Fencing Tariff Risk in Construction: How Lenders Can Protect Projects Amid Geopolitical Uncertainty

A whitepaper on how construction lenders can structure around materials cost volatility.

NEW YORK, July 30, 2025 – Our latest whitepaper deconstructs the impact of tariffs on the construction industry, and provides actionable strategies that lenders can employ to mitigate risk.

Executive summary

  • President Trump’s 2025 tariffs have increased construction material costs and reintroduced budget volatility, elevating risk for real estate development and construction lending.
  • Key mitigants for lenders include larger contingency budgets, Guaranteed Maximum Price (GMP) contracts, and early buyouts with reputable subcontractors.
  • Bravo Property Trust outlines how strategic underwriting and deal structuring can ring-fence this risk and protect investor capital.

Why do tariffs raise construction loan risk?

Tariff-driven cost volatility adds a new layer of risk to real estate deals, particularly those in the construction phase. Price hikes on steel, lumber or concrete can make pre-approved budgets obsolete. Developers may be forced to inject more equity or face defaults if contingency budgets are insufficient. For lenders, a rising-cost environment increases the risk of non-performance, stalled projects and pro formas that no longer reflect real costs.

Which building materials are affected?

  • Steel and aluminum: 25% tariffs remain in place on many foreign sources, raising core structural costs.
  • Softwood lumber: ongoing duties on Canadian lumber continue to drive price volatility, especially in wood-framed projects.
  • Concrete: uncertainty around new tariffs on Mexican concrete has raised risk for projects that rely on imported supply.
  • Finishes and mechanical items: windows, fixtures and appliances are often bought after construction starts, so price swings can hit the back half of the build.

Source: U.S. Bureau of Labor Statistics producer price data, May 2025, as cited in the whitepaper. Steel mill product prices were up 73.4% since February 2020.

How can construction lenders ring-fence tariff risk?

  • Increase contingencies: consider requiring contingency reserves above 10–15% of the hard-cost budget, depending on how much of the work was bought out before funding.
  • Require Guaranteed Maximum Price contracts: a GMP contract caps total project costs and shifts the risk of price increases to the contractor, within limits. Confirm clear escalation language for tariff-driven increases. Pair it with subcontractor default insurance or bonding.
  • Push for early buyouts: lock in pricing on core trades such as concrete and steel framing, with prequalified, financially stable subcontractors and a general contractor with a strong procurement record.

What other tools can lenders and developers use?

  • Diversified sourcing: favor domestic or tariff-safe suppliers over high-risk import markets.
  • Lock in pricing early: early trade buyouts or material pre-purchasing, rather than financial hedges, which are rarely used in middle-market construction.
  • Phased construction: it can delay exposure to future tariff shocks, but it can also raise holding and financing costs.
  • Policy engagement: supporting trade groups such as the National Association of Home Builders that seek material-specific tariff exemptions.

“Tariff volatility can’t be eliminated, but with the right protections, it can be contained.” Bravo Property Trust is a bridge and construction lender for multifamily and healthcare properties. Download the full whitepaper for the data tables and sources.